1Z0-535 Exam Questions & Answers

Exam Code: 1Z0-535

Exam Name: Primavera P6 Enterprise Project Portfolio Management Essentials

Updated: Dec 17, 2024

Q&As: 70

At Passcerty.com, we pride ourselves on the comprehensive nature of our 1Z0-535 exam dumps, designed meticulously to encompass all key topics and nuances you might encounter during the real examination. Regular updates are a cornerstone of our service, ensuring that our dedicated users always have their hands on the most recent and relevant Q&A dumps. Behind every meticulously curated question and answer lies the hard work of our seasoned team of experts, who bring years of experience and knowledge into crafting these premium materials. And while we are invested in offering top-notch content, we also believe in empowering our community. As a token of our commitment to your success, we're delighted to offer a substantial portion of our resources for free practice. We invite you to make the most of the following content, and wish you every success in your endeavors.


Download Free Oracle 1Z0-535 Demo

Experience Passcerty.com exam material in PDF version.
Simply submit your e-mail address below to get started with our PDF real exam demo of your Oracle 1Z0-535 exam.

Instant download
Latest update demo according to real exam

*Email Address

* Our demo shows only a few questions from your selected exam for evaluating purposes

Free Oracle 1Z0-535 Dumps

Practice These Free Questions and Answers to Pass the Others Oracle Certifications Exam

Questions 1

Select the true statement regarding Global Preferences in Primavera P6 EPPM Web Interface.

A. Global Preferences are shared among all users.

B. Global Preferences are customized at the user level.

C. Global Preferences are controlled by the System Administrator

D. Global Preferences are controlled by Global Security Profiles.

Show Answer
Questions 2

Where are tolerances set in Primavera P6 EPPM?

A. in Performance Thresholds

B. in Global Preferences

C. in Performance Status tab

D. in Portfolios

Show Answer
Questions 3

You received an email from a Portfolio Manager asking you to checkperformance metrics for the past months on each of the projects filtered for that portfolio.You cannot locate the portfolio that the email referenced.

What is probably the reason you cannot find the portfolio?

A. It Is a User Portfolio created by the Portfolio Manager

B. It is a User Filtered Portfolio that hasn't been refreshed.

C. You don't have the appropriate license for the Web.

D. You haven't been assigned as a resource to the projects.

Show Answer
Questions 4

You are a Portfolio Manager witha filter that has been set to identify and assignprojects to yourportfolio. You are in Primavera P6 EPPM Web Interface.

How could you be certain that the list of projects in your portfolio is complete?

A. by manually hiding projects

B. by manually adding new projects

C. by manually refreshing the filter

D. by manually updating projects

Show Answer
Questions 5

Select the true statement regarding Global Change.

A. Global change can be executed by any user.

B. Global change can modify Global Codes.

C. Global change can modify Global Security Profiles.

D. Global Change can replace existing project data with new data.

Show Answer