At Passcerty.com, we pride ourselves on the comprehensive nature of our EX0-002 exam dumps, designed meticulously to encompass all key topics and nuances you might encounter during the real examination. Regular updates are a cornerstone of our service, ensuring that our dedicated users always have their hands on the most recent and relevant Q&A dumps. Behind every meticulously curated question and answer lies the hard work of our seasoned team of experts, who bring years of experience and knowledge into crafting these premium materials. And while we are invested in offering top-notch content, we also believe in empowering our community. As a token of our commitment to your success, we're delighted to offer a substantial portion of our resources for free practice. We invite you to make the most of the following content, and wish you every success in your endeavors.
Experience Passcerty.com exam material in PDF version.
Simply submit your e-mail address below to get started with our PDF real exam demo of your EXIN EX0-002 exam.
Instant download
Latest update demo according to real exam
Which task is performed by the Change Authority?
A. Set a change budget
B. Approve or reject a request for change within approved limits
C. Refer changes that exceed budgetary limits to the Project Manager for approval
D. Update the configuration management system when a change is approved
Which statement is FALSE?
A. A project outcome perceived to be negative by one or more stakeholders is a dis-benefit
B. A project's output is any of the project's specialist products
C. A project benefit is only realized after the project has closed
D. A project outcome is the result of the change derived from using the project's outputs
Which is a purpose of the Business Case theme?
A. Identify which role is responsible for producing the Business Case
B. Identify the project's outputs
C. Establish the controls to manage changes that may impact the project benefits
D. Establish a viable investment proposition
Which is a purpose of quality planning?
A. Define the structure of the project management team
B. Detail the acceptance criteria, in order for the Project Board to agree the level of quality expected of the project's product
C. Document approval records for those project products that have met their quality criteria
D. Produce the Project Plan with resource and schedule information
If the Project Board instructs the Project Manager to implement a request for change, which document would contain details of that change?
A. Checkpoint Report
B. Highlight Report
C. Issue Report
D. Product Status Account