Passcerty.com » EXIN » Other Exin » EX0-008

EX0-008 Exam Questions & Answers

Exam Code: EX0-008

Exam Name: Agile Scrum Foundation

Updated: Dec 18, 2024

Q&As: 59

At Passcerty.com, we pride ourselves on the comprehensive nature of our EX0-008 exam dumps, designed meticulously to encompass all key topics and nuances you might encounter during the real examination. Regular updates are a cornerstone of our service, ensuring that our dedicated users always have their hands on the most recent and relevant Q&A dumps. Behind every meticulously curated question and answer lies the hard work of our seasoned team of experts, who bring years of experience and knowledge into crafting these premium materials. And while we are invested in offering top-notch content, we also believe in empowering our community. As a token of our commitment to your success, we're delighted to offer a substantial portion of our resources for free practice. We invite you to make the most of the following content, and wish you every success in your endeavors.


Download Free EXIN EX0-008 Demo

Experience Passcerty.com exam material in PDF version.
Simply submit your e-mail address below to get started with our PDF real exam demo of your EXIN EX0-008 exam.

Instant download
Latest update demo according to real exam

*Email Address

* Our demo shows only a few questions from your selected exam for evaluating purposes

Free EXIN EX0-008 Dumps

Practice These Free Questions and Answers to Pass the Other Exin Exam

Questions 1

Sprint planning should result in a commitment on what will be delivered at the end of the Sprint. Who makes this commitment?

A. The Product Owner

B. The Scrum Master

C. The team

Show Answer
Questions 2

During a Sprint, the team completes four stories with story points 3, 5, 8 and 2 respectively. They further complete half a story with a story point of 13.

What is the velocity of the team?

A. 18

B. 24.5

C. 31

Show Answer
Questions 3

A user story was estimated at five ideal hours. On a normal eight hour working day, the team gets about four hours of actual work time.

What would be the elapsed time required to complete the Story?

A. One day and two hours

B. Two days

C. Five hours

Show Answer
Questions 4

During a Sprint Planning session, the team argues about the work estimates for a particular story.

The Product Owner estimates five days.

The Lead Architect estimates two days.

The Scrum Master estimates eight days.

The team member working on it estimates seven days.

What value (in days) should be used for planning?

A. 2

B. 5

C. 7

D. 8

Show Answer
Questions 5

What should the Scrum Master advise the team to give their main focus, while working in a global distributed team?

A. Favor conference calls and video chats in order to save on travel budget.

B. Place greater emphasis on team-building activities and cultural sensitivities.

C. Provide at least four hours of overlap time by changing working hours.

Show Answer