Exam Code: P3OF
Exam Name: Portfolio, Programme and Project Offices? Foundation
Updated: Nov 17, 2024
Q&As: 150
At Passcerty.com, we pride ourselves on the comprehensive nature of our P3OF exam dumps, designed meticulously to encompass all key topics and nuances you might encounter during the real examination. Regular updates are a cornerstone of our service, ensuring that our dedicated users always have their hands on the most recent and relevant Q&A dumps. Behind every meticulously curated question and answer lies the hard work of our seasoned team of experts, who bring years of experience and knowledge into crafting these premium materials. And while we are invested in offering top-notch content, we also believe in empowering our community. As a token of our commitment to your success, we're delighted to offer a substantial portion of our resources for free practice. We invite you to make the most of the following content, and wish you every success in your endeavors.
Experience Passcerty.com exam material in PDF version.
Simply submit your e-mail address below to get started with our PDF real exam demo of your EXIN P3OF exam.
Instant download
Latest update demo according to real exam
P3O model?
A. Risk management
B. Programme planning
C. Secretariat support
D. Strategic planning or portfolio support
Which of the following describe the relationship between change and business as usual?
1.
Programmes deliver change into an organization's business operations environment
2.
Business stakeholders must be engaged appropriately about the changes being delivered
3.
Programme delivery should take priority over business as usual activities
4.
Disruption to business as usual needs to be considered when planning changes
A. 1, 2, 3
B. 1, 2, 4
C. 1, 3, 4
D. 2, 3, 4
Which role's purpose is to facilitate the development of the portfolio, programme or project dependency logs?
A. Change Control
B. Issue
C. Information Management
D. Planning and Estimating
Which P3O capability is MOST likely to result in being able to stop inappropriate programmes?
A. Reduction in resource costs
B. Ongoing alignment of programmes with strategic objectives and targets
C. Reduction in overheads dealing with conflicting resources
D. Increased ability to bundle related requests for change for programmes
Which of the following describe a decentralized P3O model?
1.
Uses hub offices to support local need
2.
Has a single office providing support to the entire organization
3.
Has a central office typically providing portfolio support
4.
Uses standards set by a central COE with local variations
A. 1,2,3
B. 1,2,4
C. 1,3,4
D. 2,3,4
Viewing Page 1 of 3 pages. Download PDF or Software version with 150 questions