At Passcerty.com, we pride ourselves on the comprehensive nature of our PRINCE2-PRACTITIONER exam dumps, designed meticulously to encompass all key topics and nuances you might encounter during the real examination. Regular updates are a cornerstone of our service, ensuring that our dedicated users always have their hands on the most recent and relevant Q&A dumps. Behind every meticulously curated question and answer lies the hard work of our seasoned team of experts, who bring years of experience and knowledge into crafting these premium materials. And while we are invested in offering top-notch content, we also believe in empowering our community. As a token of our commitment to your success, we're delighted to offer a substantial portion of our resources for free practice. We invite you to make the most of the following content, and wish you every success in your endeavors.
Experience Passcerty.com exam material in PDF version.
Simply submit your e-mail address below to get started with our PDF real exam demo of your PRINCE2 PRINCE2-PRACTITIONER exam.
Instant download
Latest update demo according to real exam
Having completed designing the plan, in which order should the next steps take place to produce a plan?
1.
Prepare Estimates
2.
Define and analyze Products
3.
Prepare the schedule
4.
Identify activities and dependencies
A. 2, 4, 3, 1
B. 4, 2, 1, 3
C. 4, 3, 2, 1
D. 2, 4, 1, 3
Which project controls should be established for the Outsourcing project?
A. Highlight Reports to the Project Manager; Exception Reports to the Project Board when project tolerances are forecast to be exceeded.
B. Highlight Reports to the Project Board; Exception Reports to corporate management when stage tolerances are forecast to be exceeded.
C. Highlight Reports to the Project Board; Exception Reports to the Project Board when stage or project tolerances are forecast to be exceeded.
Which product should register that the risk of a competitor producing a calendar at the same time was identified at the beginning of the project but the assessment of this risk appears to have been poor?
A. Issue Register
B. Follow-on action recommendations
C. Lessons Report
D. Risk Register
The project board has asked for highlight reports every six weeks during stage 3. As a result, the project manager has asked each team manager for checkpoint reports every six weeks, in order to collate these into the highlight report. The
team manager for the `marketed courses' is new to team management.
Is this an appropriate action as part of the `controlling a stage' process, and why?
A. Yes, because the project board will need to be updated with the progress of every team.
B. Yes, because checkpoint reports are a time-driven control providing progress information.
C. No, because the frequency of reporting should reflect the level of control required for the work package.
D. No, because the project board should decide on the frequency and content of progress reporting.